Focus Area |
Objective |
Sprint |
Status |
Sprint 1: 15th July- 18th July |
CCH Back Up CCH Data Migration Locally. Ensuring CCH users are working effectively locally. Installation of the Old CCH in the Server |
1-2 days 1-2 days |
Done- All files Done- Noted Files In Progress Done |
Sprint 2: 19th July- 23rd July |
Zoho Drive Upgrade of storage should be done by 19th. Moving Data from AWS to Zoho.(Copy & Paste) Installing Zoho drive to endpoints. Training if need be on Zoho drive. |
2-3 days 1 day |
MGK External Audit File is in Zoho Drive. |
Sprint 3: 24th July- 26th July |
Data check-up and ensuring the server data is in rhyme with the data locally. Stopping the AWS server and data deletion. Workdocs data can be moved to glacier storage to be a backup or to be deleted |
2-3 days |